If you first baseline the project, you can click on >View, >Tracking Gantt. Within this view, on the Gantt chart (right side), you will be able to see the Baselined data as well as the current plan. As you update your schedule bringing it in line with reality, you will always be able to compare the current plan to the baseline.

Hope this helps!

J Black

http://www.pmconnection.com

2 Responses to “how can you monitor a plan using a tracking Gantt on Microsoft project?”

  • Andy says:

    right click and use the gantt chart utility
    References :

  • jblack345 says:

    If you first baseline the project, you can click on >View, >Tracking Gantt. Within this view, on the Gantt chart (right side), you will be able to see the Baselined data as well as the current plan. As you update your schedule bringing it in line with reality, you will always be able to compare the current plan to the baseline.

    Hope this helps!

    J Black
    http://www.pmconnection.com